What is Demurrage?

Demurrage is the daily fee a port or ocean carrier charges when a container sits at the terminal past its free time, typically 4 to 7 days.

Demurrage is the daily charge an ocean carrier or marine terminal assesses when an import container stays at the port past its allotted free time. Free time at US ports typically runs 4–7 days after the container is discharged from the vessel. After that, the meter starts, and the rate commonly escalates the longer the box sits. The charge is billed to the party on the bill of lading, usually the importer, and the container is not released until it is paid.

Demurrage is one of the most expensive and most avoidable import costs. It is triggered by things the importer often does not control directly: a customs hold, a terminal appointment backlog, a chassis shortage, a dray that cannot get in. But most of it traces back to planning: documents filed late, duties unpaid, or a warehouse that was not ready to receive.

Typical cost: rates vary by port and carrier but often start around $100–$300 per container per day and climb into higher tiers after the first few days. A few containers stuck for a week during a congested stretch can erase the margin on the goods inside them.

Common mistakes: confusing demurrage (container inside the terminal) with detention (container outside the terminal); waiting for arrival to start arranging drayage; and using a warehouse so far from the port that a one-day slip in the dray schedule eats the last free day. Pre-clear customs, pre-book the dray, and confirm the warehouse dock appointment before the vessel berths.

Questions about demurrage
What is the difference between demurrage and detention?
Demurrage is charged while the container sits inside the port terminal past its free time. Detention, also called per diem, is charged while the container is outside the terminal, at your warehouse or on a dray yard, past the carrier's free days. Both are daily charges from the ocean carrier, but they cover different places and clocks.
How many free days do you get before demurrage?
Most US ports and carriers allow 4 to 7 calendar or working days after the container is discharged from the vessel, depending on the terminal and your contract. Weekends and holidays may or may not count. After free time, charges often start around $100 to $300 per day and escalate.