The ship window is the date range in which a retailer's PO must ship; the must-arrive-by date (MABD) is the deadline for it to reach the retailer's DC. Missing either triggers a chargeback.
A retail purchase order carries dates. The ship window, sometimes expressed as a ship-not-before and ship-not-after date, defines when the vendor may hand the order to the carrier. The must-arrive-by date, or MABD, is when the retailer expects the goods at its distribution center. Some retailers use a delivery window instead of a single date. The gap between the two has to accommodate transit, so a vendor shipping LTL across the country from a West Coast warehouse to an East Coast DC needs to ship early in the window.
These dates drive the warehouse calendar for retail-bound product. The routing request has to go in early enough for the retailer to assign a carrier and an appointment inside the window, and the pick has to be waved to that date. A PO that ships a day late is a chargeback; one that arrives after the MABD can be refused entirely.
Common mistakes: treating the ship window as a target rather than a boundary; routing from a warehouse too far from the DC to make the MABD by ground; and not reading the PO's dates into the WMS so the floor sees them.
Pallet count, orders per month, channels, where the containers land. An executive comes back with a real quote — within 24 business hours.